Developing Effective Work Breakdown Structures

Sunday, March 11, 2018, 6:00 AM | Leave Comment

The Work Breakdown Structure (WBS) is an often misunderstood and underappreciated tool of project management.

I would argue that it is a critical piece of the foundation of any project management methodology. Many misconceptions exist about what a WBS is, how it is used and why it is such an important part of the project management process.

A WBS is a deliverable-oriented, hierarchical grouping of the work to be executed by the project team to accomplish the project objectives and create the required deliverables. It organizes and defines the total scope of the project. Each descending level represents an increasingly detailed definition of the project work (ie decomposition).

  • What should it NOT include?

    • No reference to WHO is doing the work

    • No reference to WHEN the work is being done

    • No reference to HOW the work is being done

  • Rules for WBS attributes:

    • Use NOUNS and ADJECTIVES to describe the work

    • No dependencies, durations, resource assignments

The WBS addresses the WHAT of a project. The next step in determining the HOW is the job of the Network Diagram.

And finally, the Project Schedule will be used to determine WHEN and WHO will do the work.

A good WBS will keep you on track for delivering the full 100% scope and prevent you from scope creep.

Once you establish the 1st Level of the WBS — the real project management process begins at Level 2 and below.

How many levels do you need? Every project varies — so it should be decomposed to a sufficient level where there is a clear understanding of what the deliverable is. Or as someone very wise once said to me “Stop when it starts to get “silly”…

Courtesy of…

This column is © copyright to www.Method123.com and originally appeared in their weekly project management tip newsletter.

Use the best project management process in the world. Method123 Project Management Methodology (MPMM) is used by tens of thousands of customers around the world.

Take a test drive with the free trial download.

Buy MPMM today – NOW with extra program management and IT development modules.

Method123 Templates. There are no excuses for having crummy project management templates – not with Method123 templates a click away. Buy one or buy the complete set. Buy a multiple person license for everyone in your group.

Click here to see the full PM Kit. No excuses!

Throw us a like at Facebook.com/doable.finance


Post a Comment on Content of the Article

 

This is not a billboard for your advertisement. Make comments on the content else your comments would be deleted promptly.

CommentLuv badge