Two Essential Techniques to Manage Schedule
Sunday, May 13, 2018, 6:00 AM | Leave Comment
Managing the schedule is one of the most important activities of a project manager.
These are many great techniques to help manage the schedule.
Here are two important ones.
-
Don’t manage activities by percent complete. Manage by due date
When an activity starts it is zero percent complete. When the activity is finished it is 100% complete. In between is trickier. If a team member was 20 hours into a 40 hour activity, you could say he is 50% complete. But is he? Just because the hours are 50% used, does that mean the activity is 50% complete? Usually no.
The project manager could ask team members to report on their percent complete, but the answer is usually highly arbitrary. If a team member tells you he is 60% complete. how do you really know? How do you know he is not 58% complete or 62% complete?
A better way to get the information you need is to ask ‘When will the work be done?’ If the schedule shows an activity should be completed on Friday, and the work is not done, don’t ask the team member for the percentage complete. Instead ask the team member ‘When will the work be done?’ Asking when the work will be completed gives you concrete information you can place on your schedule, while also getting the team member to make another commitment to the new end-date.
-
Validate the work can be done in the designated time
One of the best ways to estimate work is to ask the people that will do the work. That being said, often the people that do the work were not asked for their estimate. The work was estimated by someone else. Therefore, when the project manager assigns work to a team member, it is a good practice to ask the team member to validate the estimate is correct. The team member may know immediately if the estimate is accurate, but it is also likely they may not know until they have started the work.
In general, the project manager should allow the team member to validate whether the estimate is correct. The team member is also obligated to tell the project manager if they disagree with the estimate – as soon as the team member knows. It is not acceptable to miss a due date and then claim later that the estimate was not accurate. The team member must communicate this early – as soon as they know. This allows time for options and adjustments.
Throw us a like at Facebook.com/doable.financeCourtesy of…
This column is © copyright to www.Method123.com and originally appeared in their weekly project management tip newsletter.
Use the best project management process in the world. Method123 Project Management Methodology (MPMM) is used by tens of thousands of customers around the world.
Take a test drive with the free trial download.
Buy MPMM today – NOW with extra program management and IT development modules.
Method123 Templates. There are no excuses for having crummy project management templates – not with Method123 templates a click away. Buy one or buy the complete set. Buy a multiple person license for everyone in your group.
Click here to see the full PM Kit. No excuses!